From 14:00 h of 15th of July the traffic on the latter section of “Trakia” Motorway will be opened – from road junction Zimnitsa to Karnobat
From 14:00 h tomorrow – 15th of July will be opened the traffic on the latter section of about 34 km of “Trakia” Motorway.
This is Lot 4.2 – from road junction “ Zimnitsa” to Karnobat ( from km 291+000 to km 325+280). The project “Completion of “Trakia” Motorway lots 2, 3 and 4” is co-financed by the Cohesion Fund of the European Union and the State budget of the Republic of Bulgaria through the Operational Programme “Transport” 2007-2013.
The opening of the site is from 10:30 h. The ceremony will be attended by the Chairman of the Management Board of the “Road Infrastructure Agency” eng. Lazar Lazarov.
The overall length of Lot 4 – from Yambol to Karnobat is 49,08 km. The last year, August 26th was opened the movement on Lot 4.1 – the section from Yambol to road junction “Zimnitsa” (from km. 276+200 to km. 291+000) to facilitate the traffic through “Petolachkata”. The length of the section is about 15 km.
Contractor of the construction installation works is Association JVs “Trakia IV. The contract’ value is 209 646 720,00 BGN with included VAT. The Construction supervision is performed by the Association JVs “Plan Invest – Plovdivinvest LOT4”. The Contract value is 974 400,00 BGN with included VAT. The Author’s supervision is performed by Association JVs “Viaplan-Burda”, whose contract is for 130 800 BGN with included VAT.
“Trakia” Motorway is part of the Pan European Transport Corridor VІІІ. Its construction is a priority infrastructural project of national and international importance. The overall length of the project “Completion of the construction of “Trakia” Motorway lots 2, 3 and 4” is 115 km.
The value of the grant is 699 648 287,32 BGN with included VAT. Of them 513 970 279,58 BGN are funded by the Cohesion Fund of the European Union and 185 678 007,61BGN from the State budget.