Events

HomeEventsEng. Lazar Lazarov inspected LOT 4 of “ Trakia" Motorway
Send to Friend Print Save as .DOC A+ A-

Eng. Lazar Lazarov inspected LOT 4 of “ Trakia" Motorway

Nearly 75 percent of the construction works of Lot 4 of "Trakia"Motorway  already has been completed and there are real chances to be ready by the beginning of the summer. This is for sure my last inspection as Minister of Regional Development and Public Works Lilyana Pavlova said today. This, together with the Chairman of Management Board of RIA Eng Lazar Lazarov, they went the route and are assured in the recovered rhythm of work on the site.

There are real chances, the section to be completed within the deadline  under the contract, but it means that the Builder must mobilize 200 percent and to use every good day to work on three shifts, said Pavlova. According to information reported by the contractor on the site,  yesterday was  reached an agreement with a financing institution  for the provision of working capital for payment with suppliers and to the seamlessly provision of  materials.

 „What I see today — namely, the already  prepared sections has already paved, allows me to look forward to meeting the deadline. Of all 35 facilities - bridges, overpasses and underpasses, only two are not ready yet, but I saw the hard work for them. "


Top ↑